2016 Preliminary Dam Installation

IMG_4893

Contingent on weather conditions and water availability, irrigation season is tentatively scheduled to begin on May 1, 2016.

  • April 15 – Bellota 2-foot weir & fish ladder removed, and 8-foot Bellota Weir installed.
  • April 18 – 22 – Dam installation starting upstream to downstream on Mormon Slough and Potter Creek.
  • April 25 – 29 – Dam installation starting upstream to downstream on the Old Calaveras River and Mosher Slough.
  • May 1 – Dam installation and system filling complete.

Please contact the District with any questions or concerns regarding this Preliminary Dam Installation Schedule.